Airports on Water Reading Answers: IELTS Reading Practice Test

International English Language Testing System ( IELTS )

Talk to Expert Icon BlueTalk to Expert
View more
Avleen Kaur

Avleen KaurSr. Executive Training

Updated on Oct 25, 2024 14:39 IST

The reading passage "Airports on Water" is crucial for IELTS preparation as it explores creative solutions and engineering difficulties in building airports on reclaimed land. Focusing on Japan's Kansai and Hong Kong's Chek Lap Kok, it improves comprehension, critical reading, and information analysis skills—all of which are essential for succeeding in the IELTS reading section.

IELTS Reading Airports on Water Answers 

The passage below "Airports on Water" is inspired by Cambridge 2 Test 1 Reading. You should spend about 20 minutes on Questions 1-13, based on the reading passage.

Airports on Water IELTS Reading

A. River deltas are difficult places for map makers. The river builds them up, the sea wears them down; their outlines are always changing. The changes in China's Pearl River delta, however, are more dramatic than these natural fluctuations. An island six kilometres long and with a total area of 1248 hectares is being created there. And the civil engineers are as interested in performance as in speed and size. This is a bit of the delta that they want to endure.

The new island of Chek Lap Kok, the site of Hong Kong's new airport, is 83% complete. The giant dumper trucks rumbling across it will have finished their job by the middle of this year and the airport itself will be built at a similarly breakneck pace.

B. As Chek Lap Kok rises, however, another new Asian island is sinking back into the sea. This is a 520-hectare island built in Osaka Bay, Japan, that serves as the platform for the new Kansai airport. Chek Lap Kok was built in a different way, and thus hopes to avoid the same sinking fate.

The usual way to reclaim land is to pile sand rock on to the seabed. When the seabed oozes with mud, this is rather like placing a textbook on a wet sponge: the weight squeezes the  water out, causing both water and sponge to settle lower. The settlement is rarely even: different parts sink at different rates. So buildings, pipes, roads and so on tend to buckle and crack. You can engineer around these problems, or you can engineer them out. Kansai took the first approach; Chek Lap Kok is taking the second.

C. The differences are both political and geological. Kansai was supposed to be built just one kilometre offshore, where the seabed is quite solid. Fishermen protested, and the site was shifted a further five kilometres. That put it in deeper water (around 20 metres) and above a seabed that consisted of 20 metres of soft alluvial silt and mud deposits. Worse, below it was a not-very- firm glacial deposit hundreds of metres thick.

D. The Kansai builders recognised that settlement was inevitable. Sand was driven into the seabed to strengthen it before the landfill was piled on top, in an attempt to slow the process; but this has not been as effective as had been hoped. To cope with settlement, Kansai's giant terminal is supported on 900 pillars. Each of them can be individually jacked up, allowing wedges to be added underneath. That is meant to keep the building level. But it could be a tricky task.

Conditions are different at Chek Lap Kok. There was some land there to begin with, the original little island of Chek Lap Kok and a smaller outcrop called Lam Chau. Between them, these two outcrops of hard, weathered granite make up a quarter of the new island's surface area. Unfortunately, between the islands there was a layer of soft mud, 27 metres thick in places.

E. According to Frans Uiterwijk, a Dutchman who is the project's reclamation director, it would have been possible to leave this mud below the reclaimed land, and to deal with the resulting settlement by the Kansai method. But the consortium that won the contract for the island opted for a more aggressive approach. It assembled the worlds largest fleet of dredgers, which sucked up 150m cubic metres of clay and mud and dumped it in deeper  waters. At the same time, sand was dredged from the waters and piled on top of the layer of stiff clay that the massive dredging had laid bare.

Nor was the sand the only thing used. The original granite island which had hills up to 120 metres high was drilled and blasted into boulders no bigger than two metres in diameter. This provided 70m cubic metres of granite to add to the island's foundations. Because the heap of boulders does not fill the space perfectly, this represents the equivalent of 105m cubic metres of landfill. Most of the rock will become the foundations for the airport's runways and its taxiways. The sand dredged from the waters will also be used to provide a two-metre capping layer over the granite platform. This makes it easier for utilities to dig trenches - granite is unyielding stuff. Most of the terminal buildings will be placed above the site of the existing island. Only a limited amount of pile-driving is needed to support building foundations above softer areas.

F. The completed island will be six to seven metres above sea level. In all, 350m cubic metres of material will have been moved. And much of it, like the overloads, has to be moved several times before reaching its final resting place. For example, there has to be a motorway capable of carrying 150-tonne dump-trucks; and there has to be a raised area for the 15,000 construction workers. These are temporary; they will be removed when the airport is finished.

G. The airport, though, is here to stay. To protect it, the new coastline is being bolstered with a formidable twelve kilometres of sea defences. The brunt of a typhoon will be deflected by the neighbouring island of Lantau; the sea walls should guard against the rest. Gentler but more persistent bad weather - the downpours of the summer monsoon - is also being taken into account. A mat-like material called geotextile is being laid across the island to separate the rock and sand layers. That will stop sand particles from being washed into the rock voids, and so causing further settlement. This island is being built never to be sunk. 

Score Predictor

Predict your IELTS, TOEFL, and PTE in just 4 steps!

Share 12th Board, Percentage, english score
Get estimated scores or IELTS, TOEFL & PTE


Airports on Water Questions & Answers

Questions 1-7

Complete the sentences below. 

Write NO MORE THAN TWO WORDS from the text for each answer.

1. Due to their ever-changing __________, river deltas present challenges for mapmakers.

Answer: OUTLINES
Answer location: Paragraph A
Explanation: River deltas are dynamic features subject to erosion and sediment deposition, making accurate mapping challenging. Mapmakers must navigate shifting boundaries and outlines to represent these landscapes accurately.

2. Compared to natural variations, the alterations in China's River delta are considered more __________.

Answer: DRAMATIC
Answer location: Paragraph A
Explanation: The dramatic changes in China's Pearl River delta are distinct and noticeable, indicating significant engineering initiatives and environmental effects, unlike the subtle variations observed in natural settings

3. To escape a similar __________ as Kansai airport, Chek Lap Kok was built differently.

Answer: SINKING FATE
Answer location: Paragraph B
Explanation: Chek Lap Kok, built differently, aims to prevent similar sinking issues as Kansai Airport, highlighting proactive measures during design and construction to prevent similar issues.

4.  The architects of Kansai Airport decided to create a layout around the ____________ issues.

Answer: SETTLEMENT
Answer location: Paragraph B
Explanation: Kansai's approach to addressing settlement issues, focusing on controlling ground beneath the airport, was crucial in understanding the construction challenges.

5. There was a layer of _________ between Lam Chau and Chek Lap Kok, two islands.

Answer: SOFT MUD
Answer location: Paragraph D
Explanation: Engineers faced challenges in constructing Chek Lap Kok, partly composed of granite outcrops Lam Chau and Chek Lap Kok, due to the 27-meter thick soft mud layer, causing uneven settlement.

6. Chek Lap Kok's terminal buildings only needed a small amount of ___________.

Answer: PILE-DRIVING

Answer location: Paragraph E
Explanation: The passage states that the terminal buildings, particularly in softer sections, required minimal pile-driving due to the substantial solid granite foundation.

7. in the formation of Chek Lap Kok's foundations, ________ was blasted into boulders.

Answer: GRANITE
Answer location: Paragraph E
Explanation: The passage describes a 120-meter-high granite island that was blasted and drilled into smaller stones to strengthen its foundations.








Airports on Water Answers with Location

Questions 8-13

Do the following statements agree with the information given in Reading Passage?

In boxes 8-13 on your answer sheet, write

TRUE    if the statement agrees with the information

FALSE    if the statement contradicts the information

NOT GIVEN    if there is no information on this

8. The landscape of river deltas is stable and unchanging.

Answer: FALSE
Answer location: Paragraph A
Explanation: The passage describes river deltas as dynamic landscapes, constantly changing due to natural processes like erosion and deposition, making them challenging for map makers.

9. By the middle of the year, Chek Lap Kok's construction will be finished.

Answer: NOT GIVEN
Explanation: The passage states that Chek Lap Kok is 83% complete, and construction is expected to progress quickly, but no specific timeline is provided, making it difficult to predict its completion by mid-year.

10. The local fishermen influenced the change of location for Kansai airport.

Answer: TRUE
Answer location: Paragraph C
Explanation: Kansai Airport was initially planned to be built one kilometer offshore, but local fishermen's protests led to its relocation five kilometers further, indicating a local influence.

11. the consortium decided on a cautious approach for the restoration project.

Answer: FALSE
Answer location: Paragraph E
Explanation: The text claims that the consortium chose an aggressive approach, using granite for the foundation and assembling the world's largest dredger fleet for muck removal.

12. Local laborers from the Pearl River Delta were employed for the Chek Lap Kok construction project.

Answer: NOT GIVEN
Explanation: The passage discusses the employment of local workers from the Pearl River delta in the Chek Lap Kok construction project but lacks information on their origins.

13. The island is protected from typhoons by the geotextile mat.

Answer: FALSE
Answer location: Paragraph F
Explanation: A twelve-kilometre sea wall protects Chek Lap Kok from typhoons, while a geotextile mat prevents sand from washing into rock voids, preventing settlement.







Browse universities abroad

Comments

(1289)

I am an associate professor in Physics and Awarded Ph.D. ( Tech) in Electronics and Communication Engineering (ECE). I am looking for Postdoctoral Position/ Course in Physics/Engineering on online /hybrid mode in prestigious universities abroad ( USA, UK, Singapore, Malaysia, Australia etc.) / Indi

...more

Reply to Dr Jatindranath Gain

T

Tajkia Sultana

7 months ago

Hii, I want to complete my Bachelors in Malaysia from Bangladesh. But I am not understanding which books to choose for taking preparation as I want to take preparation at home.Pls help me to choose the best books and let me know if there is any free-student scholarship in Malaysia.

Reply to Tajkia Sultana

R

Rahul Singha

7 months ago

Hello Tajkia. I would highly recommend that you opt for books/ study material that is available on the official website of IDP - the conducting body of the IELTS exam. The books would have the latest syllabus and cover everything you would need to know to ace your IELTS exam.

T

TOM Titus

12 months ago

Hi I have a query. I completed my 12th on 2017 and I been working from 2018 to 2023 can I get admission on Diploma course

Reply to TOM Titus

R

Rahul Singha

10 months ago

Hello Tom. Admission processes are university-specific. And since you have been working from 2018 to 2023 - this would only add to your resume as work experience. You can also look for assistance with university admissions from our counsellors here.

Hello shiksha I just finish my B A in political science. I want to study abroad now? Can I complete MA here. And then what kind of work will I get. I would be very happy if you answer. Thank you

Reply to Mustafijur molla

R

Rahul Singha

a year ago

Hello Mustafijur. If you are looking for assistance with applying to universities abroad. Get in touch with our Shiksha Study Abroad Counsellors and book a counselling session absolutely free, Click Here

51550871
Aditi

a year ago

Hi Shiksha Study Abroad, I have a query, I completed my bachelors in the year 2020 with first division, so can I apply on the basis of MOI?

Reply to Aditi

R

Rahul Singha

a year ago

Hello Aditi. Thank you for writing in. A Medium of Instruction Certificate (MOI) is accepted proof of English proficiency. However, whether your preferred university/ college would be considering the MOI is something you will have to check. This is entirely at the discretion of the university and th

...more